Skip to main content

Change the payment amount temporarily

Apply a temporary change to the payment amount on a contract.

Written by Jasmine

There may be occasions where you need to temporarily adjust the payment amount on a contract to accommodate a short‑term change or requirement.

To adjust the amount collected between specific dates, you'll need to make a temporary change to the existing contract. This type of update applies a temporary override to the payment schedule for one or more instalments. When doing this, you simply enter the amount you want to collect and select the start and end dates for when this temporary amount should apply.

📌Note: When changing the amount temporarily, an amendment letter isn't sent unless you have chosen to enable them. If amendment letters aren't enabled, you'll need to notify the payer directly about the price change.

📌Note: Temporary amount changes can be applied in bulk, see the guide:

📌Note: Temporary amount changes can be used for regular rolling payments on a contract without affecting any ad hoc collections.

Add a temporary amount change to a contract

  1. Click the Direct Debits tab on the left hand side.

  2. From the Quick Actions panel, select Manage Schedule.

  3. Under Find customer or contract, search by name, email address, or reference.

  4. Select the relevant customer or contract from the results list.

  5. If you select a customer, click Choose a contract and select the correct contract.

  6. Under Choose an Action, select Temporary Change and click Change Amount.

  7. Enter the temporary amount you want to collect in the box provided.

  8. Select the Start date and End date for the temporary amount change.

  9. Add a comment if you wish to include additional information.

  10. Click Save Change.

The payment amount will be updated for the selected period and return to the original amount after the patch ends.

📌Note: If the error message 'EndDate must be after StartDate' appears, please ensure the end date you select is later than the start date for the requested change. Set the end date to a suitable future date that reflects how long the temporary change is needed.


Future schedule versions

On the Schedule Versions screen, the Temporary Change appears with the date on which the change is set to begin. This section displays:

  • The type of change applied, such as an amount change

  • The updated amount that will be collected during the temporary period

  • The start and end dates that define when the temporary amount will be applied

Below the Temporary Change, you'll also see the version that the schedule returns to once the temporary period ends, showing when the normal payment amount becomes active again.

📌Note: The system blocks any new schedule version that overlaps with an existing temporary amount change. Temporary amount changes also can't extend beyond the start date of any future schedule version. In addition, a future schedule version can't be deleted until its linked temporary amount change is removed.


Delete the temporary amount change

If needed, you can remove a temporary amount change as long as it's still before the deadline for its start date. The deadline follows the same notice period used for payment requests.

To delete a temporary amount change:

  1. In Manage Schedule, go to Choose an Action and select View Versions.

  2. Find the temporary amount change in the list and select Delete Version.

  3. Click Delete to confirm and remove the scheduled temporary change.

Did this answer your question?